Demolition Status

JULY 2019 UPDATE

Demolition of the Parker Center began in the Fall of 2018; removal of the above-ground structure was completed in July 2019. The final below-ground demolition of the structure was completed in the Fall of 2019.

Demolition included the environmentally-responsible, floor-by-floor removal of the hazardous materials, followed by the deconstruction of the building, foundations, and utility tunnels.

Engineering also relocated the utilities, re-routed the fiber-optic network, and installed duct banks to bundle and protect buried cables (electrical, fiber optics, etc.). 

INTERVIEW WITH CITY ENGINEER, GARY LEE MOORE ON DEMOLITION OF PARKER CENTER

To view an interview with City Engineer, Gary Lee Moore on the demolition of Parker Center, click here.

TIME LAPSE VIDEO OF ABOVE-GROUND DEMOLITION

To view a Time-Lapse Video of the Parker Center demolition, click here